Persigo Wastewater Treatment Plant

Overview

The Persigo wastewater treatment plant in Grand Junction, Colorado processes upwards of 8.2 million gallons per day of wastewater in two anaerobic digestion tanks (primary and secondary). The facility was built in 1983 with a current rated capacity of 12.5 million gallons per day and build out of the facility will provide 25 MGD of treatment capacity. Prior to this innovative project, biogas was being captured and flared rather than beneficially utilized. In 2014, the City of Grand Junction contracted with BioCNG, LLC to design, build and operate a system to capture, collect and purify biogas to create vehicle-grade natural gas fuel, also known as renewable natural gas (RNG) or biomethane. In doing so it is estimated that approximately 460 gasoline gallon equivalents (GGEs) will be produced on-site daily and subsequently piped almost 6 miles to an existing compressed natural gas (CNG) fueling station. As of 2016, the biogas fuel powered 36 municiple natural gas vehicles, including refuse trucks, street sweepers, dump trucks and sedans - resulting in a greenhouse gas (GHG) emission reduction of 80% or more as compared to gasoline or diesel. Ten Grand Valley Transit regional buses (already equipped with natural gas engines) are also fueled by RNG, with the option to add additional buses in the future.

As the first biogas-to-vehicle fuel project in Colorado, the primary economic drivers were fuel savings and long-term fixed costs of renewable CNG fuel versus diesel and environmental credits generated under the EPA’s Renewable Fuel Standard. The total project cost, including pipeline, was approximately $2.8 million with an anticipated payback time of 7-9 years. The project will eliminate the equivalent of about 168,000 gallons of gasoline and diesel annually and prevent the release of nearly 3 million pounds of carbon dioxide into the atmosphere. The City of Grand Junction and Mesa County, CO jointly own the project. which came on-line in the spring of 2015 and has been operational since.

Financing 

The $55 million in total capital costs includes the organics receiving and processing, digestion, gas conditioning and interconnection to the SoCalGas pipeline. The digester facility occupies 4.2 acres of CR&R’s 52 acre solid waste transfer station and material recovery facility. Grants from the California Energy Commission, South Coast Quality Management District and CalRecycle partially funded the first two phases of the project. CR&R also signed contracts with 14 municipalities to provide organics collection to residents. CR&R will then charge $2.00 to $2.50 extra per household per week to collect and digest their organic waste. That new source of income will contribute funding toward the project.

Location
Persigo Wastewater Treatment Plant

Completion Date
2015

Partners:
BioCNG, LLC

Feedstock:
Wastewater

Maximum Annual Fuel Production:
~460 Gasoline Gallon Equivalents (GGEs)

Payback Period:
Estimated at 7-9 years 

Plant Cost:
$2.8 million. $500,000 came from Colorado Dept. of Local Affairs
Location: 
Persigo Wastewater Treatment Plant, 2145 River Road Grand Junction, CO, 81505